Loading...
HomeMy WebLinkAbout2025-6-6 900 King Street Hardesty & Hanover Memorandum411 Theodore Fremd Avenue Suite 206 South Rye, NY 10580 T: 914.967.6540 www.hardestyhanover.com MEMORANDUM To: Robert I. Goodman, Chairman, and the Planning Board of the Village of Rye Brook Date: June 6, 2025 Subject: Sunrise Senior Living - 900 King Street Redevelopment - Application for Approval of an Amended PUD Site Plan As requested, we have reviewed applications, correspondence and plans submitted by Sunrise Development for approval of an Amended PUD Site Plan on the property known as 900 King Street, Town of Rye Tax Map Parcel 129.68-1-13. The original PUD site plan was originally approved in June 2021. In September 2021, an Amended Site Plan was approved that reconfigured the entry driveway as a result of architectural amendments to the buildings. The current proposal involves the following amendments to the Site Plan: • Reduction of the building footprints of the Independent Living and Assisted Living buildings to reduce the building coverage from 16.5% to 15.91% • Reconfiguration of entry driveway and port cochere • Reconfiguration of the courtyards • Addition of balconies and walk-out terraces to the Independent Living building • Addition of a garden area to the Assisted Living building • Modifications to the rear loading zone, generator space and trash area • Reconfiguration of cottage garages to be 2-car garages instead of 1-car garages • Modification of the footprints of 10 of the cottages to allow a second main level bedroom There have been no modifications to the number of units or bedrooms proposed. Property Description The 17.77-acre subject property is located within the PUD district situated on the west side of King Street south of the Hutchinson River Parkway that includes The Arbors residential development and Harkness Park. It is developed with a 193,975 square-foot office building and surface parking area. The subject lot is adjacent to and west of Village Hall and the Village Firehouse, adjacent to and south of the Hutchinson River Parkway, adjacent to and east of The Arbors, and adjacent to and north of Harkness Park and the Blind Brook High School property. It is within the King Street Scenic Road Overlay District (SROD). Although the lot has 164.78 feet of frontage along King Street, it does not have direct vehicular access from King Street. Vehicular access to the lot is provided at two locations along the north side of Arbor Drive, which is currently the only access to and from King Street for the commercial and residential portions of the PUD. Review We have reviewed application materials and plans that include the following items: 1. Application for Site Plan Approval; 2. Site Plan Submittal Review Checklist; 3. Short Environmental Assessment Form 4. The following engineering plans generally entitled, “900 King Street Redevelopment” prepared by JMC Civil Engineering and Land Surveyor, last revised 5/29/2025: a. Sheet C-000, “Cover Sheet,” b. Sheet C-001, “Notes & Legends,” c. Sheet C-010, “Existing Conditions,” d. Sheet C-020, “Demolition Plan,” e. Sheet C-030, “Existing Steep Slopes Map,” f. Sheet C-040, Tree Removal/Protection Plan,” g. Sheet C-041, “Tree Removal/ Protection Chart,” h. Sheet C-100, “Layout and Striping Plan,” i. Sheet C-110, “Fire Truck, Emergency Vehicle & Truck Turning Plan,” j. Sheet C-120, “On-Site Fire Protection Plan,” k. Sheet C-130, “Intersection Sight Distance,” l. Sheet C-200, “Grading Plan,” m. Sheet C-210, “Excavation Cross Section,” n. Sheet C-211, “Road Profiles,” o. Sheet C-212, “Road Profiles,” p. Sheet C-300, “Utilities Plan,” q. Sheet C-310, “Storm Sewer Profiles,” r. Sheet C-320, “Sanitary Sewer Profiles,” s. Sheet C-400, “Erosion & Sediment Control Plan (Construction Phase 1),” t. Sheet C-401, “Erosion & Sediment Control Plan (Construction Phase 2),” u. Sheet C-402, “Erosion & Sediment Control Plan (Construction Phase 3&4),” v. Sheet C-403, “Erosion & Sediment Control Plan (Construction Phase 5),” w. Sheet C-404, “Erosion & Sediment Control Plan (Construction Phase 6),” x. Sheet C-405, “Erosion & Sediment Control Plan (Construction Phase 7),” y. Sheet C-600, “Lighting Plan,” z. Sheet C-900 – Sheet C9010, “Construction Details,” aa. Sheet L-300, “Planting Plan,” bb. Sheet L-301, “Wetland Buffer Planting Plan On-Site;” cc. Sheet L-302, “Wetland Buffer Planting Enlargement;” dd. Sheet L-303, “Wetland Buffer Planting Plan Off-Site;” ee. Sheet L-304, “Planting Details;” 5. The following architectural plans generally entitled, “900 King Street” prepared Perkins Eastman, last revised 5/29/25: a. Sheet AS-100, “Architectural Site Plan,” b. Sheet A-100, “Parking Plan,” c. Sheet A-101, “First Floor Plan,” d. Sheet A-102, “Second Floor Plan,” e. Sheet A-103, “Third Floor Plan,” f. Sheet A-104, “Fourth Floor Plan,” g. Sheet A-105, “Roof Plan,” h. Sheet A-111, Townhouse Plans,” i. Sheet A-200, “Overall Elevations,” j. Sheet A-201, “Overall Elevations,” k. Sheet A-202, “Elevations,” l. Sheet A-203, “Elevations,” m. Sheet A-204, “Elevations,” n. Sheet A-205, “Elevations,” o. Sheet A-211, “Townhouse Elevations,” p. Sheet A-301, “Typical Wall Sections.” Please note that our review is limited to planning and environmental issues. We have reviewed the revisions to the Site Plan and do not have any further comments. We look forward to discussion with the Board. Sarah L. Brown, AICP Associate, Principal Planner cc: Honorable Mayor and the Village Board of Trustees Christopher Bradbury, Village Administrator Michal Nowak, Superintendent of Public Works/Village Engineer Jennifer L. Gray, Esq., Village Attorney Robert Zitt, Esq., Village Attorney