HomeMy WebLinkAbout900 King Street HDR Environmental Review Technical Memo 2021-6-11
hdrinc.com
P a g e | 1
Environmental Review Technical Memo
Date: Friday, June 11, 2021
Project: 900 King Street Redevelopment
To: Chairman Robert Goodman and Members of the Village of Rye Brook Planning
Board
cc: Jennifer Gray, Michal Nowak, Chris Bradbury
From: HDR: Noemi Castillo
Michael Musso
Subject: Review of Supplemental Materials for PUD Site Plan documentation (Air
Quality, Noise, Vibration and Hazardous Materials), provided May 27, 2021
Introduction
Henningson Durham & Richardson Architecture and Engineering, PC (HDR) performed
a review of the supplemental Site Plan application submittals prepared for the property
located at 900 King Street (AKRF; dated May 27, 2021) This review was completed for
purposes of determining if previous HDR Site Plan comments have been- addressed.
The May 27, 2021 supplemental Site Plan submittals were prepared by the Applicant to
address comments received from the Village of Rye Brook and its consultants, including
HDR, on the Revised Site Plan application submittals. ). HDR previously submitted to the
Village Planning Board two Environmental Review Technical Memos (dated April 5 and
May 7, 2021).. Our technical reviews of the Site Plan continue to focus on compliance
with the Air Quality, Noise, Vibration, and Hazardous Materials sections of the November
2020 Final Environmental Impact Statement (FEIS) and associated Findings Statement.
The May 27, 2021 Supplemental Site Plan Application Planning Board Submission, that
is the subject of this review, included:
• Transmittal document reviewed
• A: Required Content not reviewed
• B: Consultant Response Memo reviewed
• C: JMC Site Plans Sheet Updates reviewed
• D: Construction Management Plan – updated Section 10.1.2 reviewed
o Final Appendix: Construction Noise Barrier Efficacy Assessment Report reviewed
P a g e | 2
As listed above, the May 27, 2021 submittal included a Construction Noise Barrier
Efficacy Assessment Report (noise barrier analysis), as an appendix to the Construction
Management Plan. HDR participated on conference calls with AKRF, Jennifer Gray and
Sarah Brown on April 1, 2021, where the applicant’s noise barrier analysis was first
discussed, and ideas on the visual appearance of the noise barriers were discussed.
AKRF provided a draft of this noise barrier analysis to HDR on April 15, 2021. HDR
reviewed and provided to AKRF preliminary comments on the draft noise analysis on
April 23 and April 30, 2021. A revised draft of the noise barrier analysis was provided to
HDR on May 7, 2021; HDR reviewed and provided preliminary comments to AKRF on
May 20, 2021. In addition, HDR participated in additional conference calls with AKRF on
April 27, May 4,May 12, and May 21, 2021 to discuss HDR’s comments prior to the formal
(May 27) submittal to the Planning Board.
This Environmental Review Technical Memo provides a review of outstanding HDR
comments on the Site Plan application submittals received to date, including the
Construction Noise Barrier Efficacy Assessment Report.
Construction Noise Barrier Efficacy Assessment Report, dated May 27, 2021
• With the exception of HDR’s comment to provide the Planning Board with a cover
letter for this analyses and report, HDR’s preliminary comments, provided on April
23, April 30, and May 20, 2021 have been generally addressed.
• Since the purpose of the Noise Barrier Efficacy analysis is not to alter the FEIS
construction noise analysis conclusions or requirements, or the areas at which
the FEIS found the potential for construction noise impacts, the first paragraph on
page 6, after Table 5, should be deleted.
• Appendix D should be updated based on HDR’s previous comments on Tables 1
through 5 of the report. The calculated difference results in Appendix D are at
times not comparing to the same receptor, with and without the western and
eastern barriers. This should be rectified. As at times multiple receptors were
modeled to represent a location (e.g., Arbors Condos), the difference for each
receptor should be determined and then the range reflected in the Appendices.
• HDR has no further comments on the analytical methods themselves. However,
since the construction is expected to result in noise level increases greater than
6 dBA at the Arbors Condos and the Village Hall, Police Department and Fire
Department, it is recommended that:
o The Applicant obtain weekday and weekend baseline measurements at
the receptors, including Arbors Condos, Blind Brook High School,
Harkness Tennis Court, the Village Hall, Police Department, Fire
Department, and King Street residencies, no earlier than two weeks prior
to the initiation of construction and demolition activities. This data should
P a g e | 3
be submitted to the Village Building Department prior to on-site activities
commencing.
o The Planning Board should consider the following conditions to the Site
Plan approval, to reflect what was assumed by AKRF in the Construction
Noise Barrier Efficacy noise models:
Pile Driving (impact and vibratory), blasting, jack hammering, and
rock crushing activities are not permitted absent further review by
the Village Building Department and, if requested, by the Village’s
Special Engineering Consultant. (These were not included in the
noise analyses, and therefore should be restricted from occurring.)
On-site activities shall be limited to the site disturbance boundaries
shown on the Construction equipment per phase (Phase 1 through
6) drawings attached to the May 7, 2021 preliminary Construction
Noise Barrier Efficacy Assessment Report.
Delivery trucks shall be required not to idle engines.
Revised Construction Management Plan (CMP), dated May 27, 2021
Construction Noise
• As per HDR’s preliminary comments on the noise barrier analysis, Section 10 of
the CMP should include the following statement, since these activities/noise
sources were not included in the noise model: “Pile Driving (impact and
vibratory), blasting, jack hammering, and rock crushing activities are not
permitted absent further review by the Village.”
Comments on the Site Plan Approval Drawings dated May 27, 2021
Construction Noise
• The AKRF Response to Comments Memo, dated May 27, 2021, states that the
S&E Plan Legend has been updated on drawing C-010 to show three separate
types of fencing. These three types include the 6’ high noise barrier, the 12’ high
noise barrier and the 6’ chain link fence, all shown with different symbols on the
plans. However, this does not appear to have been completed.
Operational Noise
• As requested by the Village Board during the May 13, 2021 Planning Board
meeting, AKRF should revise the April 14, 2021 Outdoor Mechanical Equipment
– Acoustical Impact Assessment Report to more clearly explain the presented
results. Table 2 of this report should be modified to differentiate between the
modeled predicted noise levels of the proposed mechanical equipment and the
Total Future Noise Level (i.e., existing noise level plus proposed mechanical
equipment noise level).