PUD Concept Plan 250-7E(4)(a)[1][a][i]Location of Site in relation to surrounding community C-000
PUD Concept Plan 250-7E(4)(a)[1][a][ii]Property Lines, street names, zoning C-000
PUD Concept Plan 250-7E(4)(a)[1][a][ii]Names of adjoining property owners C-100
PUD Concept Plan 250-7E(4)(a)[1][a][iii]Existing conditions, including topography and woods C-100
PUD Concept Plan 250-7E(4)(a)[1][a][iv]Location witdths of proposed streets and pedestrian ways C-300
PUD Concept Plan 250-7E(4)(a)[1][a][v]Land Use Plan, showing open space, buffers, recreation areas C-300; Tech Memo Secs. 3.1, 3.8
PUD Concept Plan 250-7E(4)(a)[1][a][vi]Parking Plans C-300; A-100
PUD Concept Plan 250-7E(4)(a)[1][a][vii]Utilities C-500
PUD Concept Plan 250-7E(4)(a)[1][a][viii]Zoning Comparison Chart for Existing and Proposed Zoning C-000
PUD Concept Plan 250-7E(4)(a)[1][b][i]Text Description of Plan Tech Memo, Secs. 2, 3.1
PUD Concept Plan 250-7E(4)(a)[1][b][ii]Name and address of Applicant and professionals C-000
PUD Concept Plan 250-7E(4)(a)[1][b][iii]Proposed methods of ownership, control and future operation Tech Memo Sec. 2.2.2
PUD Concept Plan 250-7E(4)(a)[1][b][iv]Construction Schedule Tech Memo, Sec. 3.14
PUD Concept Plan 250-7E(4)(a)[1][b][v]List of Approvals Tech Memo, Sec 1.5
Preliminary Site Plan 209-3C(1)(a)SBL C-000
Preliminary Site Plan 209-3C(1)(a)Property Card Tech Memo, Appendix B-1
Preliminary Site Plan 209-3C(1)(b)Location Map C-000
Preliminary Site Plan 209-3C(1)(d)Survey Map, topography, setback of existing structures C-100
Preliminary Site Plan 209-3C(1)(e)Adjacent street: location, name, width, curblines C-100
Preliminary Site Plan 209-3C(1)(f)Location and owners of all adjoining lands C-100
Preliminary Site Plan 209-3C(1)(g)[1]Deed to Property Tech Memo, Appendix B-3
Preliminary Site Plan 209-3C(1)(g)[2]All Easements Tech Memo, Appendix B-3
Preliminary Site Plan 209-3C(1)(g)[3]Existing and Proposed Deed restrictions or coveneants
Existing-Tech Memo Appendix B-
3; Proposed-None
Preliminary Site Plan 209-3C(1)(h)Existing Zoning C-000
Preliminary Site Plan 209-3C(1)(i)Prior Land Use Approvals Tech Memo, Sec. 3.1
Preliminary Site Plan 209-3C(1)(j)Other legal agreements required by PB or BoT N/A
Preliminary Site Plan 209-3C(2)(a)Location of watercourses, streams, wetlands C-100; Tech Memo 3.3
Preliminary Site Plan 209-3C(2)(b)2-foot contours C-100
Preliminary Site Plan 209-3C(2)(c)Boundaries of areas subject to flooding N/A
Preliminary Site Plan 209-3C(2)(d)Rock Outcroppings and Steep Slopes C-120
900 King Street List of Plans Required
Pg 2 10/26/2017
Required For Code Section Requirement Location In Submission
Preliminary Site Plan 209-3C(2)(e)Tree Survey
C-130, C-131 and Tech Memo
Sec. 3.5, Appendix D-4
Preliminary Site Plan 209-3C(2)(f)Aquifers N/A
Preliminary Site Plan 209-3C(3)(a)Location of existing building on- and off-site C-100
Preliminary Site Plan 209-3C(3)(b)Location of existing roods and sidewalks C-100
Preliminary Site Plan 209-3C(3)(c)
Location, dimension, grade, flow direction of existing sewer,
culverts, waterlines and other underground utilities C-100
Preliminary Site Plan 209-3C(3)(d)Other Site improvements C-100
Preliminary Site Plan 209-3C(4)(a)
Grading and drainage plan, showing existing and proposed
contours, new grades indicating clearly how such grades will
meet existing grades of adjacent properties or the street and
calculations of expected storm drain loads to be
accommodated by the proposed drainage system.C-400; SWPPP
Preliminary Site Plan 209-3C(4)(b)
Location, design, type of construction, proposed use and
exterior dimensions, including length, width, ground floor
elevation and height, of all buildings.C-400; A-series
Preliminary Site Plan 209-3C(4)(c)
Location, design and type of construction of all parking and
truck loading areas, showing access and egress.C-300; A-100
Preliminary Site Plan 209-3C(4)(d)Provision for pedestrian access.C-300
Preliminary Site Plan 209-3C(4)(e)
Location, size and proposed screening of outdoor storage
areas, if any.N/A
Preliminary Site Plan 209-3C(4)(f)
Location, design and construction material of all existing or
proposed site improvements, including drains, culverts,
retaining walls, landscape walls and fences.
C-300; C9xx; Specifications
during Site Plan Approval
Preliminary Site Plan 209-3C(4)(g)
Description of the method of sewage disposal and storm
drainage location, design and construction material of such
facilities.C-500, Tech Memo Sec. 3.9
Preliminary Site Plan 209-3C(4)(h)
Description of the method of securing public water and
location, design and construction material of such facilities.C-500, Tech Memo Sec. 3.9
Preliminary Site Plan 209-3C(4)(i)
Location of fire and other emergency zones, including the
location of fire hydrants.C-320; C-500
Preliminary Site Plan 209-3C(4)(j)
Location, design and construction materials of all energy
distribution facilities, including electrical, gas and solar energy.
C-500; specifications during Site
Plan Approval
Preliminary Site Plan 209-3C(4)(k)
Location, size, wording, design, color, illumination and type of
construction of all proposed signs.
C-300; specifications during Site
Plan Approval
900 King Street List of Plans Required
Pg 3 10/26/2017
Required For Code Section Requirement Location In Submission
Preliminary Site Plan 209-3C(4)(l)
Location and proposed development of all buffer areas,
including existing vegetative cover.L-100
Preliminary Site Plan 209-3C(4)(m)
Location, type, design, shielding and hours of operation of
outdoor lighting facilities.
C-600; specifications during Site
Plan Approval
Preliminary Site Plan 209-3C(4)(n)
Identification of the location and amount of building area
proposed for retail sales or similar commercial activity.N/A
Preliminary Site Plan 209-3C(4)(o)
Landscape plan with a plant schedule that includes the
common name, scientific name, height and/or spread, nursery
condition, and quantities of all plant material proposed and
specifications and details for plant installation and postplanting
maintenance.
L-100; specifications during Site
Plan Approval
Preliminary Site Plan 209-3C(4)(p)
Estimate of earthwork showing the quantity of any material to
be imported to and/or removed from the site.C-400; Tech Memo 3.2
Preliminary Site Plan 209-3C(4)(q)
Description of measures planned to assure proper erosion and
sedimentation control in accordance with the requirements of
Chapter 118 entitled "Erosion and Sediment Control," of the
Code of the Village of Rye Brook.C-200
Preliminary Site Plan 209-3C(4)(r)An estimated project construction schedule.Tech Memo Sec. 3.14
Preliminary Site Plan 209-3C(4)(s)
Record of application for and approval status of all necessary
permits from state and county officials and local utility
companies.During Site Plan Approval
Preliminary Site Plan 209-3C(4)(t)
Identification of any federal, state or county permits required
for the project's execution, including project referrals, if any,
and environmental review procedures mandated by Article 8,
Environmental Quality Review, of the Environmental
Conservation Law (SEQRA).Tech Memo Sec. 1.5
Preliminary Site Plan 209-3C(4)(u)
The outlines of any proposed easements, deed restrictions or
covenants.N/A - None Proposed
Preliminary Site Plan 209-3C(4)(v)
For a change of use in an existing shopping center...parking
study N/A
Preliminary Site Plan 209-3C(4)(w)
For a change of use in an existing shopping center...traffic
study N/A
Preliminary Site Plan 209-3C(5)Other elements deemed necessary by BoT or PB Tech Memo
Preliminary Site Plan 209-3D Storwmater management plan consistent with Chapter 217 SWPPP; Tech Memo 3.4
Preliminary Site Plan 209-3F Required Affordable Housing Tech Memo Secs. 2 and 3.1
Preliminary Site Plan 235-9A Tree Removal Map
C-130, C-131 and Tech Memo
3.5
900 King Street List of Plans Required
Pg 4 10/26/2017
Required For Code Section Requirement Location In Submission
Preliminary Site Plan 235-18A Tree Restoration Plan
L-100; Tech Memo 3.5;
specifications during site plan
approval
Final Site Plan 209-14 Parks Required Tech Memo 3.8
Final Site Plan 235-9B Tree Preservation Map
Tech Memo 3.5; Specifications