HomeMy WebLinkAbout2019.06.25 References for Demolition Management and Logistics PlanReferenced Materials
DRAFT 10 6/25/2019
The potential environmental impacts of demolishing the existing office building were documented
in the environmental review of the application to redevelop the Project Site. Specifically, and in
addition to the material submitted as part of the demolition application, inclusive of the demolition
plan set, the potential impacts of demolition were analyzed in the following documents, which are
incorporated by reference into the record for this application:
Draft Environmental Impact Statement (DEIS) for the 900 King Street Redevelopment.
Adopted by the Rye Brook Board of Trustees on September 12, 2018; and,
preliminary Final Environmental Impact Statement (pFEIS) for the 900 King Street
Redevelopment. Submitted by the Applicant. May 14, 2019.
The Draft Demolition Management and Logistics Plan (“Plan”) relies on the analyses in those
documents. As such, the Plan explicitly incorporates and addresses the relevant substantive
comments received on the DEIS by the public as well as by Village Boards, staff, and professional
consultants.
Below are detailed cross-references to the analyses on which the various portion of this Plan are
based. The cross-references are provided in the same order as the analyses in Section C of the
Plan.
DUST CONTROL
DEIS. Section 16.3.3, “Construction: Air Quality.”
pFEIS. Section 2.16.2.3, “Construction: Air Quality.”
pFEIS. Section 3.16, “Construction: Air Quality.” Comment & Response #146.
NOISE
pFEIS. Section 2.16.2.4, “Construction: Noise.”
o DEIS Appendix G, “Noise Fundamentals,” prepared by AKRF, Inc., September
12, 2018.
o pFEIS Appendix J, “Construction Period Noise Analysis,” prepared by AKRF,
Inc., September 12, 2018.
pFEIS. Section 3.16, “Construction: Noise and Vibration.” Comments & Responses #147-
149
TRAFFIC
DEIS. Section 16.3.2, “Construction: Traffic and Transportation.”
o DEIS Figure 16-1, “Conceptual Construction and Estimated Manpower
Schedule,” prepared by AP Construction, September 18, 2018.
o DEIS Appendix F, “Traffic Impact Study,” prepared by Maser Consulting P.A.,
August 24, 2018.
pFEIS. Section 2.16.2.2, “Construction: Traffic and Transportation.”
pFEIS. Section 3.16, “Construction: Traffic and Transportation.” Comments & Responses
#139-145.
EROSION AND SEDIMENT CONTROL
DEIS. Section 16.3.1, “Erosion & Sediment Control.”
pFEIS. Section 2.16.2.1, “Erosion & Sediment Control.”
pFEIS. Section 3.16 – “Construction: General.” Comment & Response #138.
Demolition Management and Logistics Plan
DRAFT 11 6/25/2019
STEEP SLOPES
{Same references as “Erosion & Sediment Control”}
HAZARDOUS MATERIALS
DEIS. Chapter 15, “Hazardous Materials.”
o DEIS Appendix H-1, “Phase I Environmental Site Assessment,” prepared by
AKRF, Inc., October 2017.
o DEIS Appendix H-2, “Phase II Environmental Site Assessment,” prepared by
AKRF, Inc., January 2018.
pFEIS. Section 2.15, “Hazardous Materials.”
pFEIS. Section 3.15, “Hazardous Materials.” Comment & Response #132.
VIBRATION
DEIS. Section 16.3.5, “Construction: Vibration.”
pFEIS. Section 2.16.2.5, “Construction: Vibration.”
pFEIS. Section 3.16, “Construction: Noise and Vibration.” Comment & Response #150.
TREE REMOVAL
DEIS Appendix D-4, “Tree Survey with Condition,” prepared by AKRF, Inc., September
18, 2018.
Volume 4, “Engineering and Architectural Plans: PUD Concept Plan & Preliminary Site
Plans,” prepared by JMC Engineering. Sheet C-130 and C-131, last updated 5/14/2019.
WATERS AND WETLANDS
DEIS. Chapter 5, “Waters and Wetlands.”
o DEIS Appendix D-2, “Wetland Delineation Report,” prepared by AKRF, Inc.,
September 21, 2017.
o DEIS Appendix D-5, “Wetland Functional Assessment,” prepared by AKRF,
Inc., June 28, 2018.
pFEIS. Section 2.5, “Waters and Wetlands.”